CONVEYOR IDLER ASSEMBLY REMOVAL AND INSTALLATION - Continued
Figure 1. Conveyor Chain -- Removal.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1186    1187    1188    1189    1190  1191  1192    1193    1194    1195    1196  
img
. . . . .
TM 5-3895-385-23-2
0417
FIELD MAINTENANCE
BITUMINOUS MATERIAL PAVING MACHINE (BMPM)
CONVEYOR DRAG CHAIN REMOVAL, INSTALLATION, AND ADJUSTMENT
INITIAL SETUP:
Tools and Special Tools
References
General Mechanics Tool Kit (GMTK) (WP 0440, Vol
TM 5-3895-385-10
3, Item 64)
WP 0418
Suitable lifting device (500 lb (227 kg) minimum)
WP 0419
Web sling (WP 0440, Vol 3, Item 66)
Equipment Conditions
Materials/Parts
BMPM lifted off the ground and properly supported
Cotter pin (2) (WP 0439, Vol 3, Item 86)
(WP 0435)
Estimated Time to Complete Task
Pin (2) (WP 0439, Vol 3, Item 77)
2.5 hr
Personnel Required
91L
Assistant
CONVEYOR DRAG CHAIN REMOVAL, INSTALLATION, AND ADJUSTMENT
NOTE
Conveyor drag chain assembly removal and installation steps are the same for both sides of the
Bituminous Material Paving Machine (BMPM). Left side shown.
0417-1