TM 5-3895-385-23-2
FIELD MAINTENANCE
BITUMINOUS MATERIAL PAVING MACHINE (BMPM)
SCREED EXTENSION VERTICAL ADJUSTMENT SCREW REMOVAL AND INSTALLATION
INITIAL SETUP:
Tools and Special Tools
Personnel Required
91L
General Mechanics Tool Kit (GMTK) (WP 0440, Vol
Equipment Conditions
3, Item 64)
Screed extension vibrator hydraulic hose clamp
Materials/Parts
Locking nut (WP 0439, Vol 3, Item 44)
Screed extension slide plate assembly removed
Locking nut (WP 0439, Vol 3, Item 43)
Locking nut (WP 0439, Vol 3, Item 50)
Estimated Time to Complete Task
5.5 hr
SCREED EXTENSION VERTICAL ADJUSTMENT SCREW REMOVAL AND INSTALLATION
NOTE
Procedure is the same for all screed extension vertical adjustment screws. Left screed extension
inner screed extension vertical adjustment screw shown.