Table 1. Fuse Box Malfunction Troubleshooting Procedures -- Continued
Table 1. Electric Generator Malfunction Troubleshooting Procedures -- Continued

Field Maintenance Manual For Bituminous Material Paving Machine - 1 Page Navigation
  1049    1050    1051    1052    1053  1054  1055    1056    1057    1058    1059  
img
. . . .
TM 5-3895-385-23-1
0214
FIELD MAINTENANCE
BITUMINOUS MATERIAL PAVING MACHINE (BMPM)
ELECTRIC GENERATOR MALFUNCTION
INITIAL SETUP:
Test Equipment
References -- Continued
Hydraulic test kit (WP 0440, Vol 3, Item 59)
WP 0370, Vol 2
Multimeter (WP 0440, Vol 3, Item 37)
WP 0373, Vol 2
Personnel Required
WP 0391, Vol 2
91L
WP 0441, Vol 3
Assistant
WP 0442, Vol 3
References
WP 0443, Vol 3
WP 0106
WP 0445, Vol 3
WP 0107
WP 0447, Vol 3
WP 0277, Vol 2
WP 0449, Vol 3
WP 0279, Vol 2
WP 0451, Vol 3
WP 0291, Vol 2
Equipment Conditions
WP 0295, Vol 2
Engine off (TM 5-3895-385-10)
WP 0313, Vol 2
Hydraulic oil cool (TM 5-3895-385-10)
WP 0357, Vol 2
Engine hood assembly removed (WP 0433, Vol 2)
TROUBLESHOOTING PROCEDURES
NOTE
The maintainer should only use this troubleshooting Work Package (WP) if directed to do so from
another troubleshooting WP. The procedures below assume it has been determined there is a
malfunction with the electric generator and not the electric screed heater box.
Table 1. Electric Generator Malfunction Troubleshooting Procedures.
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
1. Generator malfunction.
1. Install fuse box (WP 0277, Vol
2).
2. Connect battery cables (WP
0357, Vol 2).
3. Start Bituminous Material Paving
Machine (BMPM) engine (TM 5-
3895-385-10).
0214-1