TM 5-3895-373-20
2.24.2. JACKING AND CRIBBING Continued.
C.
JACKING
AND
CRIBBING
FOR
TRACK
MAINTENANCE.
Paving machine weighs approximately 21,400 lbs (9707
kg). Ensure machine is securely supported before
performing any maintenance. Severe personal injury or
death
may
occur
from
not
supporting
machine
adequately prior to maintenance.
NOTE
Paving machine may be driven up on 4 in. high x 12 in.
wide x 8 ft long cribbing; go to step 2.
If using single point overhead lift per paragraph 2.24.4,
go to step 2.b and steps 2.e through 2.k.
1. RAISE AND CRIB PAVING MACHINE ON 4 IN.
CRIBBING.
NOTE
During these steps, one side of paving machine is raised
at a time.
a. Move paving machine to level concrete pad. If
concrete pad is not available, use steel plates to
distribute jack load over larger area.
GO TO NEXT PAGE
2-448