TM 5-3895-373-10
1.
Remove strikeoff extension assembly using the following steps.
(1)
Remove hex head cap screw (45) and flat washer (44).
(2)
Remove
self-locking
nuts
(40),
flat
washers (39), and hex head cap screws
(38).
Remove
strikeoff
extension
assembly (37). Hardware will be used
during installation of endgate assembly.
Reinstall hardware onto strikeoff extension
assembly (37).
m.
Remove the bolt-on screed extension frame
using the following steps.
WARNING
To avoid personal injury, do not
attempt to lift and remove the bolt-on
screed extension frame alone. Bolt-
on screed extension frame weighs
approximately 57 lbs (25,9 kg). Use a
second person to help hold the
extension
frame
during
removal.
Failure to do so may result in serious
injury.
(1)
With the help of a second person to
support the bolt-on screed extension
frame (34), remove hex head cap screws
(35) and flat washers (36).
(2)
With one person holding the front end and
another holding the rear end, lift and
remove bolt-on screed extension frame
(34) from paving machine.
CAUTION
During removal of screed extension
plate, ensure that the spacers and
plate
spacers
around
the
studs
securing the screed extension plate
to the frame are not allowed to move
or fall from the stud. If spacers or
plate spacers are moved and not
returned to their initial position on
the screed plate, a screed alignment
is required.
(3)
With the help of a second person, remove
screed extension plate (29) by removing
self-locking nuts (27) and flat washers
(28). Carefully lower and remove screed
extension plate from extension screed
frame (6).
(4)
Secure spacers (30 and 31) and plate
spacers (32) onto screed extension plate
(29) with flat washers (28) and self-locking
nuts (27). When reinstalling screed
extension
plate,
spacers
and
plate
spacers must be installed in the same
locations from which they were removed.
2-92