Figure 5. Left Torque Hub Hydraulic Hoses.
HYDRAULIC TANK REMOVAL AND INSTALLATION

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  479    480    481    482    483  484  485    486    487    488    489  
img
. . .
TM 5-3895-385-23-2
0302
Torque Hub Hydraulic Hose Installation -- Continued.
9. Install four bolts (Figure 5, Item 1), new lock washers (Figure 5, Item 2), and two retaining clamps (Figure 5,
Item 3) and connect hydraulic hose 1A (Figure 5, Item 7) onto left torque hub motor (Figure 5, Item 17).
10. Connect hydraulic hose 13 (Figure 5, Item 4), hydraulic hose 8 (Figure 5, Item 6), and hydraulic hose 11
(Figure 5, Item 8) onto left torque hub motor (Figure 5, Item 17).
11. Install four bolts (Figure 5, Item 16), new lock washers (Figure 5, Item 15), and two retaining clamps (Figure
5, Item 14) and connect hydraulic hose 1B (Figure 5, Item 5) onto left torque hub motor (Figure 5, Item 17).
12. Install two new lock nuts (Figure 5, Item 13), flat washers (Figure 5, Item 12), bracket (Figure 5, Item 11), and
spacer (Figure 5, Item 10) onto BMPM (Figure 5, Item 9).
END OF TASK
FOLLOW-ON TASK
1. Lower BMPM to ground (WP 0435).
2. Remove lifting device.
3. Install engine hood assembly (WP 0433).
4. Verify proper operation.
5. Dispose of hydraulic oil and wiping rags In Accordance With (IAW) local Standard Operating Procedure
(SOP).
END OF TASK
END OF WORK PACKAGE
0302-11/12 blank