• Home
  • Download PDF
  • Order CD-ROM
  • Order in Print
Figure 2. Left Pedestal Assembly.
PLATFORM CONTROL REMOVAL AND INSTALLATION

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  252    253    254    255    256  257  258    259    260    261    262  
img
.
TM 5-3895-385-23-2
0261
Left Pedestal Assembly Removal -- Continued.
3. Remove eight bolts (Figure 2, Item 3) and 16 lock washers (Figure 2, Item 2) from pedestal assembly.
Discard lock washers.
4. Remove pedestal assembly (Figure 2, Item 1) from pedestal assembly mounting bracket (Figure 2, Item 4).
END OF TASK
Left Pedestal Assembly Installation
1. Install pedestal assembly (Figure 2, Item 1) onto pedestal assembly mounting bracket (Figure 2, Item 4).
2. Install eight bolts (Figure 2, Item 3) and 16 new lock washers (Figure 2, Item 2) onto pedestal assembly
(Figure 2, Item 1).
3. Connect six electrical connectors (Figure 2, Item 5).
4. Install three bolts (Figure 2, Item 6), new lock washers (Figure 2, Item 7), flat washers (Figure 2, Item 8), and
lower pedestal cover (Figure 2, Item 9) onto pedestal assembly.
END OF TASK
FOLLOW-ON TASK
1. Set BATTERY DISCONNECT switch to ON (TM 5-3895-385-10).
2. Verify proper operation.
END OF TASK
END OF WORK PACKAGE
0261-5/6 blank