TM 5-3895-373-34
SECTION VIII. TRACK ASSEMBLY MAINTENANCE
Para
Page
Repair Track Tensioning Cylinder ....................................................................... 2.39
2-535
Replace Track Chain Assembly .......................................................................... 2.41
2-558
Replace Track Frame.......................................................................................... 2.34
2-495
Replace Track Rollers ......................................................................................... 2.35
2-501
Replace Track Tensioning Cylinder .................................................................... 2.37
2-514
Replace/Repair Track Drive Hub......................................................................... 2.40
2-544
Replace/Repair Track Idler Roller Assembly....................................................... 2.36
2-506
Replace/Repair Track Tensioning Relief Valve and Unloading Valve................. 2.38
2-518
2.34
REPLACE TRACK FRAME.
This task covers:
a.
Removal
b.
Replace
INITIAL SETUP
Tools:
General mechanics automotive tool kit
(Item 106, Appendix D)
Chain assembly (Item 29, Appendix D)
Torque wrench (Item 134, Appendix D)
Track frame offset wrench (Item 24, Appendix C)
Transmission jack (Item 55, Appendix D)
Materials/Parts:
Thread locking compound (Item 13, Appendix B)
Thread locking compound solvent (Item 32, Appendix B)
Lockwashers
Track frame
Personnel Required:
Two 62B construction equipment repairers. Second
person needed to assist hoisting track frame.
References:
TM 5-3895-373-20
TM 5-3895-373-24P
Equipment Condition:
Screed tow arm removed per TM 5-3895-373-20.
Paving machine jacked up and cribbed (for track
maintenance)
per TM 5-3895-373-20.
Track chain assembly removed per paragraph 2.41.
Track idler roller assembly removed per paragraph 2.36.
Track tensioning cylinder removed per paragraph 2.37.
Track rollers removed per paragraph 2.35.
NOTE
There are two track frames on the
paving machine, one on the right side
and one on the left side. Remove the
screed
tow
arm
and
track
chain
components from the side being worked.
GO TO NEXT PAGE
2-495