TM 5-3895-373-10
2.12
TRAVELING PROCEDURE.
a.
Start the paving machine per paragraph 2.10.
b.
On gauge panel do the following:
(1)
Place the throttle control switch in the
MAX position.
(2)
Lift screed to the travel position using
screed lift switch and close screed travel
lock valve per paragraph 2.1.4.
(3)
Place the throttle control switch in a
position to achieve desired speed. Select
desired speed by rapidly moving throttle
control switch to IDLE then to center
detent.
(4)
Move the speed range switch on the
operator control console to the up, "hare",
travel position.
(5)
Place the travel switch in the UP, forward/
reverse "F/R" position.
2-35