Figure 1. Bulkhead Wiring Harness.
SCREED WIRING HARNESS REMOVAL AND INSTALLATION

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  954    955    956    957    958  959  960    961    962    963    964  
img
.
TM 5-3895-385-23-2
0377
Bulkhead Wiring Harness Removal -- Continued.
NOTE
It will be necessary to remove cable ties from cables.
1. Disconnect W11 J1 (Figure 1, Item 8) from screed (Figure 1, Item 9).
2. Disconnect W11 J2 (Figure 1, Item 2) from W1 J15 (Figure 1, Item 1).
3. Disconnect W11 J3 (Figure 1, Item 11) from left auger bypass hydraulic solenoid (Figure 1, Item 12).
4. Disconnect W11 J4 (Figure 1, Item 10) from left conveyor variable speed hydraulic solenoid (Figure 1, Item
3).
5. Disconnect W11 J5 (Figure 1, Item 7) from right auger bypass hydraulic solenoid (Figure 1, Item 4).
6. Disconnect W11 J6 (Figure 1, Item 6) from right conveyor variable speed hydraulic solenoid (Figure 1, Item
5).
END OF TASK
Bulkhead Wiring Harness Installation
1. Connect W11 J6 (Figure 1, Item 6) to right conveyor variable speed hydraulic solenoid (Figure 1, Item 5).
2. Connect W11 J3 (Figure 1, Item 11) to left auger bypass hydraulic solenoid (Figure 1, Item 12).
3. Connect W11 J4 (Figure 1, Item 10) to left conveyor variable speed hydraulic solenoid (Figure 1, Item 3).
4. Connect W11 J5 (Figure 1, Item 7) to right auger bypass hydraulic solenoid (Figure 1, Item 4).
5. Connect W11 J2 (Figure 1, Item 2) to W1 J15 (Figure 1, Item 1).
6. Connect W11 J1 (Figure 1, Item 8) to screed (Figure 1, Item 9).
END OF TASK
FOLLOW-ON TASK
1. Install cable ties where necessary.
2. Set BATTERY DISCONNECT switch to ON (TM 5-3895-385-10).
END OF TASK