Roller Idler Assembly Removal -- Continued.
Roller Idler Assembly Installation -- Continued.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1251    1252    1253    1254    1255  1256  1257    1258    1259    1260    1261  
img
.
TM 5-3895-385-23-2
0425
Roller Idler Assembly Installation
Figure 2. Roller Idler Assembly.
WARNING
The bogie shaft weighs 78 lb (38 kg). Two personnel or a suitable lifting device is necessary to lift
component. Failure to comply may cause injury or death to personnel.
CAUTION
Properly support the item being lifted. Failure to comply may cause damage to equipment.
1. Install bogie shaft (Figure 2, Item 1), eight bolts (Figure 2, Item 3), and new lock washers (Figure 2, Item 2)
onto BMPM with assistance.