Figure 8. Conveyor Chain -- Installation.
Figure 9. Conveyor Chain Adjustment.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1214    1215    1216    1217    1218  1219  1220    1221    1222    1223    1224  
img
TM 5-3895-385-23-2
0419
Conveyor Drive Motor Installation -- Continued.
8. Install chain onto sprocket (Figure 8, Item 5).
9. Install chain master link (Figure 8, Item 3) and two new cotter pins (Figure 8, Item 4).
10. Adjust conveyor chain tension (perform Conveyor Chain Adjustment task).
END OF TASK
0419-13