Auger Drive Chain Adjustment -- Continued.
Figure 1. Auger Assembly Strap Points.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1144    1145    1146    1147    1148  1149  1150    1151    1152    1153    1154  
img
. .
TM 5-3895-385-23-2
0408
FIELD MAINTENANCE
BITUMINOUS MATERIAL PAVING MACHINE (BMPM)
AUGER LIFT HYDRAULIC CYLINDER REMOVAL, INSPECTION, AND INSTALLATION
INITIAL SETUP:
Tools and Special Tools
Equipment Conditions
General Mechanics Tool Kit (GMTK) (WP 0440, Vol
Cutoff shoes closed and augers lowered (TM 5-
3, Item 64)
3895-385-10)
Cap and plug set (WP 0440, Vol 3, Item 11)
BATTERY DISCONNECT switch OFF (TM 5-3895-
385-10)
Drain pan (WP 0440, Vol 3, Item 15)
Estimated Time to Complete Task
Materials/Parts
0.5 hr
Cotter pin (2) (WP 0439, Vol 3, Item 82)
Wiping rag (1) (WP 0439, Vol 3, Item 89)
Personnel Required
91L
AUGER LIFT HYDRAULIC CYLINDER REMOVAL, INSPECTION, AND INSTALLATION
NOTE
The steps for removing and installing auger lift hydraulic cylinders are the same for both the
left-side and right-side cylinders. Right side shown.
Some hydraulic oil will leak out of hoses and hydraulic fittings when disconnecting or
connecting components. Have a drain pan and rags in place to capture hydraulic oil.
0408-1