AUGER DRIVE CHAIN REMOVAL, INSTALLATION, AND ADJUSTMENT
Figure 2. Auger Chain Master Link.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1136    1137    1138    1139    1140  1141  1142    1143    1144    1145    1146  
img
.
TM 5-3895-385-23-2
0407
Auger Drive Chain Removal
Figure 1. Auger Chain Top and Bottom Covers -- Removal.
1. Remove six bolts (Figure 1, Item 13), lock washers (Figure 1, Item 12), inside auger chain top cover (Figure 1,
Item 1), and inside auger chain bottom cover (Figure 1, Item 11) from auger frame (Figure 1, Item 2). Discard
lock washers.
2. Remove two bolts (Figure 1, Item 5), lock washers (Figure 1, Item 4), and outside auger chain top cover
(Figure 1, Item 3) from auger frame (Figure 1, Item 2). Discard lock washers.
3. Remove two grease fitting bolts (Figure 1, Item 9), lock washers (Figure 1, Item 8), bolts (Figure 1, Item 7),
lock washers (Figure 1, Item 6), and outside auger chain bottom cover (Figure 1, Item 10) from auger frame
(Figure 1, Item 2). Discard lock washers.