Figure 2. ECM.
ELECTRONIC CONTROL MODULE (ECM) REMOVAL AND INSTALLATION - Continued

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  1086    1087    1088    1089    1090  1091  1092    1093    1094    1095    1096  
img
.
TM 5-3895-385-23-2
0399
ECM Installation -- Continued.
Figure 3. ECM Connections.
2. Connect W1 J3 and W1 J39 (Figure 3, Item 7) onto output module ECM (Figure 3, Item 1).
3. Connect W1 J1 (Figure 3, Item 6) onto screed controller ECM (Figure 3, Item 2), and tighten screw (Figure 3,
Item 5).
4. Connect W1 J2 (Figure 3, Item 4) onto propel controller ECM (Figure 3, Item 3), and tighten screw (Figure 3,
Item 5).
END OF TASK