Fuse Box Installation-- Continued.
1. Install fuse box (Figure 22, Item 1), four bolts (Figure 22, Item 3), and flat washers (Figure 22, Item 4) onto
BMPM (Figure 22, Item 5).
2. Connect W1 J4 (Figure 22, Item 2) onto W13 J1 (Figure 22, Item 1).
3. Connect W1 J10 (Figure 22, Item 6) onto W13 J2 (Figure 22, Item 7).
END OF TASK
FOLLOW-ON TASK
1. Set BATTERY DISCONNECT switch to ON (TM 5-3895-385-10).
2. Verify proper operation.
END OF TASK
END OF WORK PACKAGE