Figure 15. Terminal Block.
Figure 17. Relay.

Field Maintenance Manual For Bituminous Material Paving Machine - 2 Page Navigation
  336    337    338    339    340  341  342    343    344    345    346  
img
.
TM 5-3895-385-23-2
0277
Fuse Box Assembly -- Continued.
Figure 16. Relay Block.
13. Install four wires (Figure 16, Item 8) into relay block (Figure 16, Item 4) connectors.
14. Install retaining tab (Figure 16, Item 7) into relay block (Figure 16, Item 4).
15. Install nut (Figure 16, Item 1), new lock washer (Figure 16, Item 2), flat washer (Figure 16, Item 5), screw
(Figure 16, Item 6), and relay block (Figure 16, Item 4) into fuse box panel (Figure 16, Item 3).