Ignition Switch Wiring Harness Removal -- Continued.
1. Remove screw (Figure 1, Item 1) and disconnect green and white wire (Figure 1, Item 3) from emergency
stop contact 2 side 2 (Figure 1, Item 2).
2. Remove screw (Figure 1, Item 1) and disconnect two green and white wires (Figure 1, Item 15) from
emergency stop contact 1 side 1 (Figure 1, Item 16).
3. Remove screw (Figure 1, Item 8) and disconnect green and white wire (Figure 1, Item 9) from keyless engine
switch contact AC (Figure 1, Item 7).
4. Remove screw (Figure 1, Item 10) and disconnect red wire (Figure 1, Item 12) from keyless engine switch
contact 30 (Figure 1, Item 11).
5. Remove screw (Figure 1, Item 5) and disconnect yellow wire (Figure 1, Item 4) from keyless engine switch
contact 50 (Figure 1, Item 6).
6. Disconnect W5 J1 (Figure 1, Item 14) from W1 J11 (Figure 1, Item 13).
END OF TASK
Ignition Switch Wiring Harness Installation
1. Connect W5 J1 (Figure 1, Item 14) to W1 J11 (Figure 1, Item 13).
2. Connect yellow wire (Figure 1, Item 4) and install screw (Figure 1, Item 5) onto keyless engine switch contact
50 (Figure 1, Item 6).
3. Connect red wire (Figure 1, Item 12) and install screw (Figure 1, Item 10) onto keyless engine switch contact
30 (Figure 1, Item 11).
4. Connect green and white wire (Figure 1, Item 9) and install screw (Figure 1, Item 8) onto keyless engine
switch contact AC (Figure 1, Item 7).
5. Connect two green and white wires (Figure 1, Item 15) and install screw (Figure 1, Item 1) onto emergency
stop contact 1 side 1 (Figure 1, Item 16).
6. Connect green and white wire (Figure 1, Item 3) and install screw (Figure 1, Item 1) onto emergency stop
contact 2 side 2 (Figure 1, Item 2).
END OF TASK
FOLLOW-ON TASK
1. Install pedestal top (WP 0261).
2. Install Batteries (WP 0357).
3. Verify proper operation.
END OF TASK