Table 2-1. ORGANIZATIONAL PREVENTIVE MAINTENANCE CHECKS AND SERVICES
Q--Quarterly
S-Semiannually
A-Annually
B-Biennially
H-Hours
M-Miles
ITEM
INTERVAL
ITEM TO BE INSPECTED
NO.
Q S A B H Ml PROCEDURE :Check for and have repaired,filled,or adjusted
as needed.
NOTE
PERFORM OPERATOR/CREW PMCS PRIOR TO OR IN CON-
JUNCTION WITH ORGANIZATIONAL PMCS IF:
a. There is a delay between the daily operation of the equipment
and the organizational PMCS.
b.
Regular operator is not assisting/participating.
ELECTRICAL SYSTEM
1
Check wiring harness for corrosion and bare wires. Replace defective
wiring.
2
Check all lights for proper operation. Replace defective lamps and
lights.
DISTRIBUTOR BODY
3
Check material storage tank, subframe, tie downs and fasteners for
obvious damage, weld breaks. Notify DS Maintenance for repair.
4
Check that manhole cover seals properly. Repair as needed.
5
Check overflow pipe. Clean any material buildup in pipe.
UNIVERSAL DRIVE
6
Check universal drive and U-joints. Check for wear and cracks. Re-
place damaged U-joints.
HYDRAULIC SYSTEM
7
Check all hydraulic lines and fittings. If damaged, replace.
BURNER FUELSYSTEM
8
Check fuel lines and fittings. If damaged, replace.
9
Check burner fuel tank holding straps. If damaged, repair or replace.
10
Check burner assembly air hose for leeks. Replace if damaged.