TM 5-3895-371-10
h.
Vent 3-way valve at supply tank end, so that pump can draw the material out of the filling hose.
i.
After draining filling hose, place intake valve lever (4) down for circulation of material in tank.
2-6.
Filling Through Manhole.
a.
NOTE
Should pump fail to function properly, check, clean, and reinstall discharge strainer (para 3-13).
b.
If you do not want material to enter pump and circulating system, have intake valve lever (27, fig. 1-1 ) in
extreme up position
c.
If you expect to heat material further in distributor, allow sufficient space for expansion
d.
If distributor is to be filled with hot bitumen, proceed cautiously if there is any moisture in tank, or if
emulsion was used in the previous load VV-D-1078A may be used to prevent foaming
NOTE
The discharge filter often becomes clogged when the manhole strainer is not used, or when rags and debris are
2-7.
a.
Place the control levers (see fig. 2-9 for location) in the following positions
(1)
Quadrant Control Lever - Circulate and fill
(2)
Intake Valve Lever - Down
(3)
Butterfly Valve Lever - Out (normal)
(4)
Drain Valve Lever - Forward
(5)
Transfer Valve Lever - Distribute
(6)
Vacu-flo Valve Lever - Up
2-15