TM 5-3895-373-20
Several paving machine components received special
processing
for
shipment
including
tiedown
and/or
protective lubrication coatings. Unpack the paving
machine as follows:
a.
Using cleaning cloths (Item 7, Appendix C), wipe
protective grease from surface of control console
guide shaft (1). Dispose of used cleaning cloths
in accordance with local procedures.
b.
Remove tape securing air cleaner cap assembly
(2) and protective cap (3).
c.
Remove hex nuts (4), flat washers (5), and hex
head cap screws (6) from screed tow arm (7).
Remove hex head cap screws (8), flat washers
(9), and shipping bracket (10). Repeat shipping
bracket removal for tow arm on opposite side of
paving machine. Store all hardware and shipping
brackets in the toolbox.
2-4