TM 5-3895-373-20
REFERENCE INFORMATION
SCREED VIBRATOR CIRCUIT
Remove operator switch panel per paragraph 7.6 to gain
access to screed vibrator switch terminals.
To avoid reversing polarity to the voltmeter, connect
negative test lead to equipment ground and use positive
lead to probe for voltage.
Refer to the electrical system diagram at the end of the
manual for equipment wiring details.
Open gauge panel access doors per TM 53895-373-10
to gain access to circuit breakers.
If paving machine moves, +12 vdc is at output terminals
of travel switch.
Refer to paragraph 7.21 for harness and lead wire repair.
2-333